Mr.Sebby's Achievements
Single Status Update
-
Update March 14, 1pm by Octave Klaba : 1/3 Still working on restarting of the A optical network in SBG1. We hope to have the network A UP today. It will allow us to redeploy the internal tools locally. Reconstruction of the B optical network will take 2 days. Lot of fibers have to connected.
Update March 14, 1pm 2/3 240V in SBG1 is ready to be tested. Tomorrow 20KV for SBG1 will be UP. The 20KV is SBG3 is in progress. 2 days. Watercooling SBG1/3/4 checked and protected. Cleaning and drying are in progress.
Update March 14, 1pm 3/3 60 tech work on the site. Still lot of to do, but it’s going faster that expected. We keep the same ETA and maybe we will be faster.
A webpage with the final state of:
- primary data
-internal backup (not contractual)
- service backup is in progress.